PLEASE DRAW THE NETWORK DIAGRAM AND FILL THE TABLE WITH GIVEN INFORMATION
Important Dates/Datelines for Project Schedule Revisions:
2-8 activity revised start date T1*= 30 (in other words this activity MUST be start at 30th day!)
10-14 activity revised start date T2*= 55
10-18 activity revised start date T3*= 35
14-22 activity revised start date T4*= 60
X IS THE LAST NUMBER OF YOUR UNIVERSITY ID
Critical Path | activity
i-j |
Duration
tij |
i Node
TEi TGi |
j Node
TEj TGj |
i-j Activity
tEBij tESij tGBij tGSij |
Floats
TBij SBij |
||||||
0 – 2 | X | 0 | 20 | 20 | 30 | 0 | 10 | 20 | 30 | 20 | 10 | |
0 – 4 | 12 | 0 | 20 | 12 | 37 | 0 | 12 | 25 | 37 | 25 | 0 | |
0 – 6 | 9 | 0 | 20 | 9 | 54 | 0 | 9 | 45 | 54 | 45 | 0 | |
2 – 8 | 15 | 20 | 30 | 35 | 45 | 20 | 35 | 30 | 45 | 10 | 0 | |
4 – 8 | 6 | 12 | 37 | 35 | 45 | 12 | 18 | 39 | 45 | 27 | 17 | |
4 – 10 | X | 12 | 37 | 35 | 45 | 12 | 20 | 37 | 45 | 25 | 15 | |
4 – 12 | – | 12 | 37 | 16 | 61 | 12 | 12 | 61 | 61 | 49 | 4 | |
6 – 12 | 7 | 9 | 54 | 16 | 61 | 9 | 16 | 54 | 61 | 45 | 0 | |
8 – 10 | – | 35 | 45 | 35 | 45 | 35 | 35 | 45 | 45 | 10 | 0 | |
8 – 14 | 11 | 35 | 45 | 60 | 60 | 35 | 46 | 49 | 60 | 14 | 14 | |
10 – 14 | 5 | 55 | 55 | 60 | 60 | 55 | 60 | 55 | 60 | 0 | 0 | |
10 – 16 | 9 | 35 | 45 | 44 | 54 | 35 | 44 | 45 | 54 | 10 | 0 | |
10 – 18 | 6 | 35 | 45 | 41 | 58 | 35 | 41 | 52 | 58 | 17 | 0 | |
12 – 20 | 13 | 16 | 61 | 48 | 74 | 16 | 29 | 61 | 74 | 45 | 19 | |
18 – 20 | 7 | 41 | 58 | 48 | 74 | 41 | 48 | 67 | 74 | 26 | 0 | |
18 – 22 | 12 | 41 | 58 | 70 | 70 | 41 | 53 | 58 | 70 | 17 | 17 | |
14 – 22 | 10 | 60 | 60 | 70 | 70 | 60 | 70 | 60 | 70 | 0 | 0 | |
16 – 22 | 16 | 44 | 54 | 70 | 70 | 44 | 60 | 54 | 70 | 10 | 10 | |
18 – 24 | 14 | 41 | 58 | 85 | 85 | 41 | 55 | 71 | 85 | 30 | 30 | |
20 – 24 | 11 | 48 | 74 | 85 | 85 | 48 | 59 | 74 | 85 | 26 | 26 | |
22 – 24 | 15 | 70 | 70 | 85 | 85 | 70 | 85 | 70 | 85 | 0 | 0 |
QUESTION 2.
Find a site plan (mobilization plan) of a real project that shows site units (workshops, technical office, stores, dormitories, tower cranes and the construction area itself …), service roads (haul roads), walkways.. i.e transportation plan, utilities (water, drainage, electricity …), prevailing wind, nearby structures etc. (Just copy and paste)
Please give your critics according to the information given in our course.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more
Recent Comments