You are the Information Systems Project Manager for ABC, Incorporated. To improve the administration of XYZ, Inc. your company has been contracted to install a new computer system in XYZ’s corporate headquarters and in all five of their district offices. A development team consisting of the PM, SA, SO, and Sr. HT have determined that the following list of activities is key to completing the project. Your job is to lay out the project using Project Managing Software:
Project Rubric
ITEM | Points | Comments |
Correct Use of PM Software | ||
Activities Entered (5 for list; 10 for duration) | 15 | |
Predecessors Entered | 10 | |
Resources entered (including overtime): 10 for Resource sheet; 15 for Assigning Resources | 25 | |
Paths & Critical Path & Number of days | 25 | |
Overall Cost of the Project | 25 | |
TOTAL | 100 |
To complete this project, it will be necessary for you to ensure that you have the proper tools to do it. The following tools will be used in this project:
There are different ways to obtain a screen capture. On a PC you can press the CTRL key and the Print Screen key. Then you can past the captured screen into the document. Pressing Shift-Command-3 on a Mac will capture the current screen on the Mac and place a file of this capture on the desktop. You can also use your own Screen Capture Software if wanted.
You are to turn in your Microsoft Project or Project Libre File that contain your work. Make sure that you complete all Items in the rubric. You will also turn in a word document answering the 2 questions at the bottom of this document.
Task |
Task Name |
Duration |
Personnel |
Percent of Assigned Time |
1 | Prepare preliminary systems design and obtain approval | 20 | Project Mgr
Systems Analyst SysOps Sr. Hardware Tech |
25
75 25 25 |
2 | Prepare detailed systems design | 20 | Project Mgr
Systems Analyst SysOps Sr. Hardware Tech |
50
50 25 25 |
3 | Select equipment | 15 | Project Mgr
Systems Analyst SysOps Sr. Hardware Tech |
25
25 75 75 |
4 | Order and receive equipment | 30 | Project Manager
Contracting Agent Equipment |
10
20 |
5 | Prepare sites for installation | 5 | 1 Sr. Hardware Tech
2 Hardware Techs |
100
100 |
6 | Install equipment | 30 | 1 Sr. Hardware Tech
2 Hardware Techs |
100
100 |
7 | Conduct total systems test | 10 | SysOps
|
100 |
8 | Develop user’s manual | 30 | Tech writer
Editor Sysops Sr. Hardware Tech |
100
25 5 10 |
9 | Train users on system | 10 | SysOps
Sr. Hardware Tech |
100
100 |
Resource Sheet
Personnel | Contract Billing Per Hour ($) |
Project Manager | 80 |
Systems Analyst | 55 |
SysOps | 75 |
Sr. Hardware Tech | 65 |
Hardware Tech | 58 |
Contracting Agent | 45 |
Tech Writer | 45 |
Editor | 50 |
Predecessors: The Project team has determined that 1 must precede 2 must precede 3 must precede 4. 3 must precede 5 must precede 6 must precede 7. 4 & 7 must precede 8 must precede 9.
Assume a work week is 40 hours, Monday through Friday. Overtime rate is 1 ½ times the contract cost. Holiday rate is 2 times the contract cost. However, XYZ, Inc. has not authorized any use of overtime or holiday rates. The start date for the project is June 15.
Make sure you fill out RESOURCES SHEET and assign them! You only need to complete Resource Name and Standard Rate. This is found under Task, then click the down arrow by Gantt Chart.
CREATE a Gantt chart, Network Diagram, Resource Sheet of this Project. The Network Diagram is created as you are creating the Gantt Chart.
Assign resources as listed in the tables above to the Gantt chart. This is done on the Gantt Chart. Highlight which task you want to assign the resources to, then right click and choose Assign Resources. Choose the right person and enter the percent as shown on the table on page 1.
What are the different paths and what is the critical path and how long is it? Look at the Network Diagram to determine the different paths and calculate how long each path is and determine the Critical Path.
If the cost of equipment is $350,000, what is the overall contracted cost of the project? Add this to the cost of all the different employees for the total cost of the project. To find this information, go to Project, Project Information then click Statistics.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more
Recent Comments